Mon 9 Nov 2026, 09:30
Grid and subsidy
9 of 11 projects have open DISCOM or subsidy steps · oldest wait first
Waiting on the DISCOM3KP-1035, KP-1033, KP-1031
Waiting on you2KP-1040, KP-1036
Documents missing1KP-1042, DCR certificate
Median feasibility wait9Working days · last 8 applications, range 4 to 18
| Project | Step now | Since | Next | Owner |
|---|---|---|---|---|
| KP-1035 | Feasibility awaited | Thu 22 Oct 18 d | Call the DISCOM 15 working days against a median of 9 | Pooja Sharma |
| KP-1040 | Not applied | Design approved Thu 29 Oct, 11 d | Prepare the application PO-0316 also waiting | Pooja Sharma On you |
| KP-1041 | Feasibility approved | Fri 30 Oct | Install not booked: inverter 3 days late, Narmada | Sameer Khan |
| KP-1033 | Net meter awaited | Inspection passed Mon 2 Nov, 7 d | – | DISCOM |
| KP-1039 | Feasibility approved | Mon 2 Nov | Install Thu 12 Nov, Crew B | – |
| KP-1029 | Subsidy Claimed | Tue 3 Nov, 6 d | Credit to the customer awaited | National portal |
| KP-1042 | Feasibility approved | Fri 6 Nov | DCR certificate missing Vardhan PV · install tomorrow | Sameer Khan |
| KP-1031 | Inspection tomorrow, Tue 10 Nov | – | Crew B supports the inspection | Imran Shaikh |
| KP-1036 | Installing, day 2 today | – | Completion report due Wed 11 Nov | Pooja Sharma On you |
TemplateIn use on 11 projects
Madhya Pradesh west (Indore) v3
- Documents
- 11
- Form fields
- 16
- Inspection
- Median 4 working days after the report, last 6
Common rejection reasonsChecked on every claim
1Name on the bill differs from the name on the portal
2Capacity in the application differs from the commissioning report
3Module serials not on the DCR certificate
4Photos without location or date
5Bank details missing on the portal