Grid and subsidy

9 of 11 projects have open DISCOM or subsidy steps · oldest wait first

Waiting on the DISCOM3KP-1035, KP-1033, KP-1031
Waiting on you2KP-1040, KP-1036
Documents missing1KP-1042, DCR certificate
Median feasibility wait9Working days · last 8 applications, range 4 to 18
ProjectStep nowSinceNextOwner
KP-1035Feasibility awaitedThu 22 Oct 18 dCall the DISCOM
15 working days against a median of 9
Pooja Sharma
KP-1040Not appliedDesign approved Thu 29 Oct, 11 dPrepare the application
PO-0316 also waiting
Pooja Sharma On you
KP-1041Feasibility approvedFri 30 OctInstall not booked: inverter 3 days late, NarmadaSameer Khan
KP-1033Net meter awaitedInspection passed Mon 2 Nov, 7 d–DISCOM
KP-1039Feasibility approvedMon 2 NovInstall Thu 12 Nov, Crew B–
KP-1029Subsidy ClaimedTue 3 Nov, 6 dCredit to the customer awaitedNational portal
KP-1042Feasibility approvedFri 6 NovDCR certificate missing
Vardhan PV · install tomorrow
Sameer Khan
KP-1031Inspection tomorrow, Tue 10 Nov–Crew B supports the inspectionImran Shaikh
KP-1036Installing, day 2 today–Completion report due Wed 11 NovPooja Sharma On you
TemplateIn use on 11 projects
Madhya Pradesh west (Indore) v3
Documents
11
Form fields
16
Inspection
Median 4 working days after the report, last 6
Open the template
Common rejection reasonsChecked on every claim
1Name on the bill differs from the name on the portal
2Capacity in the application differs from the commissioning report
3Module serials not on the DCR certificate
4Photos without location or date
5Bank details missing on the portal