Mon 9 Nov 2026, 09:30

KP-1042 · Vikram Bhosale

Installation

5.4 kWp residential, on-grid · Vidya Nagar, Indore · Owner Pooja Sharma

Project plan Download DISCOM set
WonEngineeringProcurementInstallationDISCOM and net meterHandover
Net-metering applicationSubmitted on the DISCOM's portal · reference NM-2026-118204
Feasibility approved
1
Application submittedMon 2 Nov · Pooja Sharma
2
Technical feasibility approved by the DISCOMFri 6 Nov · approval letter filed below
3
Installation by Kiranpath SolarTue 10 to Wed 11 Nov · Crew A, Raju Yadav · photos come from the job card
4
Work completion report to the DISCOMPlanned Thu 12 Nov · built from the as-built design and the crew's photos
5
DISCOM inspectionPlanned Mon 16 Nov · the DISCOM confirms the date after the report
6
Net meter installedPlanned Wed 18 Nov · done by the DISCOM
7
Commissioning and synchronisationPlanned Thu 19 Nov
Documents7 of 11 ready
DocumentComes fromNeeded forStatus
Net-metering application formFilled by SurgePV from the projectApplicationSubmitted
Latest electricity billUploaded at the lead stageApplicationAttached
Consumer ID and address proofUploaded by PoojaApplication, subsidyAttached
Single line diagram (SLD)Heaven DesignsHD-20417 rev BApplicationAttached
DISCOM drawing set (PDF)Heaven DesignsHD-20417 rev BApplicationAttached
Feasibility approval letterDISCOM, Fri 6 NovInstallationFiled
Module and inverter datasheetsEquipment databaseReport, subsidyAttached
DCR certificate for the 12 modulesVardhan PV, with PO-0319SubsidyNot received
Asked at delivery, GRN-0294, Fri 6 Nov
Installation photosRaju's job cardReport, subsidyAfter installation
Work completion reportFilled by SurgePV from the as-builtInspectionAfter installation
Commissioning reportDISCOM, after inspectionSubsidyAfter commissioning
Subsidy claimNot started
PM Surya Ghar, central₹78,000₹30,000 × 2 kW + ₹18,000 for the third kW
Where
National portal, in Vikram's name
Owner
Pooja Sharma
Opens
After commissioning, planned Thu 19 Nov
Paid to
Vikram's bank account

Shown apart from the price. Vikram pays the full ₹3,02,400; the subsidy reaches him after the claim.

DCR certificate still missing The subsidy claim cannot be filed without it. It is needed by commissioning, planned Thu 19 Nov. Ask Vardhan PV again
Your DISCOM's checklist

The document list and form formats come from the template for the DISCOM on this connection. Each utility asks for a slightly different set, so the list can be edited per project.