Mon 9 Nov 2026, 09:30
Projects in execution
11 projects between won and handover. 3 installations this week, 1 purchase order waiting for Nikhil.
In execution11Won, not yet handed over
Installing this week3KP-1036, KP-1042, KP-1039
Waiting on the DISCOM3Inspection, net meter, feasibility
Waiting for approval1PO-0316 for KP-1040, Nikhil
Search id, customer or PO
Owner: anyone
Crew: any
BoardList
Engineering2
KP-1043AJ
Designing in-house in the studio
In design
KP-1044AJ
Requested from Heaven Designs, HD-20452
With Heaven Designs
Procurement2
KP-1040SK
PO-0316 to Sunline Distributors, ₹96,410
Waiting for approval
Needs Nikhil Rao
KP-1041SK
PO-0317 to Narmada Electricals
Partly delivered
Inverter was due Fri 6 Nov, not received
Installation3
KP-1036RY
Crew A, day 2 of 2 today
On site today
KP-1042RY
Vikram Bhosale
5.4 kWp · Crew A, Tue 10 to Wed 11 Nov
Materials in store
Owner Pooja Sharma
KP-1039IS
Crew B, Thu 12 to Fri 13 Nov
Scheduled
DISCOM and net meter3
KP-1031IS
DISCOM inspection Tue 10 Nov, Crew B supports
Inspection booked
KP-1033PS
Inspection passed, net meter not fitted yet
Net meter awaited
KP-1035PS
Application submitted, no reply from the DISCOM
Feasibility awaited
Handover1
KP-1029PS
Commissioned, handover pack sent
Subsidy claim pending
Cards move when a person changes the stage; nothing moves on its own. Leads before won stay on the sales pipeline.