Projects
Mon 9 Nov 2026, 09:30
KP-1042 · Vikram Bhosale
Installation5.4 kWp residential, on-grid · Vidya Nagar, Indore · Owner Pooja Sharma
WonEngineeringProcurementInstallationDISCOM and net meterHandover
Installation starts tomorrow, Tue 10 Nov, with Crew A (Raju Yadav)
All 9 buy-list items are in the store: the Malwa order since Thu 5 Nov and the 12 Vardhan PV modules since Fri 6 Nov. DISCOM feasibility was approved Fri 6 Nov.
Milestones4 of 11 done · dates after installation are planned
| Milestone | Owner | Date | Status |
|---|---|---|---|
| Won, advance recorded Proposal v2, ₹3,02,400 | Pooja Sharma | Wed 28 Oct | Done |
| Engineering approved HD-20417, design rev B, option A, re-approved by Vikram | Aditya Jain | Fri 30 Oct | Done |
| DISCOM net-metering application NM-2026-118204, submitted Mon 2 Nov, feasibility approved Fri 6 Nov | Pooja Sharma | Fri 6 Nov | Done |
| Materials received, 2 purchase orders PO-0318 Malwa, Wed 4 Nov, earthing shortfall closed Thu 5 Nov · PO-0319 Vardhan PV modules, Fri 6 Nov | Sameer Khan | Fri 6 Nov | Done |
| Installation, 2 days Crew A, 3 people | Raju Yadav | Tue 10 to Wed 11 Nov | Starts tomorrow |
| Work completion report to the DISCOM | Pooja Sharma | Thu 12 Nov | Planned |
| DISCOM inspection Date set by the DISCOM after the report | Raju Yadav | Mon 16 Nov | Planned |
| Net meter installed Fitted by the DISCOM | DISCOM | Wed 18 Nov | Planned |
| Commissioning | Raju Yadav | Thu 19 Nov | Planned |
| Subsidy claim on the national portal ₹78,000, opens after commissioning | Pooja Sharma | After commissioning | Planned |
| Handover Serials, as-built, handover pack | Pooja Sharma | Thu 19 Nov | Planned |
PaymentsRecorded here, collected outside SurgePV
| Milestone | Share | Amount | Status |
|---|---|---|---|
| Advance | 20% | ₹60,480 | Received Wed 28 Oct, UPI |
| On material delivery | 70% | ₹2,11,680 | Received Sat 7 Nov Invoiced Fri 6 Nov |
| On commissioning | 10% | ₹30,240 | Invoice on commissioning |
| Received so far | ₹2,72,160 | of ₹3,02,400 |
Subsidy of ₹78,000 is paid by the government to Vikram after the claim. It is not part of these payments.
Ready for installation5 of 6
Send reminder on WhatsApp
A help list, not a gate. The crew can start either way.
Team
PSPooja SharmaSales, project owner, paperwork
AJAditya JainDesign engineer
SKSameer KhanPurchase
RYRaju YadavCrew A lead, crew of 3
Activity
70% payment received, ₹2,11,680
Sat 7 Nov · Pooja
70% invoice sent to Vikram, all material in
Fri 6 Nov · Pooja
DISCOM feasibility approved
Fri 6 Nov · Pooja
Modules received, GRN-0294, 12 of 12 serials scanned
Fri 6 Nov, 14:40 · Sameer
Third earthing kit received, GRN-0292, shortfall closed
Thu 5 Nov, 11:00 · Sameer
Malwa order received, GRN-0291, earthing 2 of 3
Wed 4 Nov, 16:30 · Sameer
PO-0318 and PO-0319 approved and sent
Mon 2 Nov, 14:36 · Nikhil