Schedule

KP-1042 · install, day 1 of 2

Tue 10 Nov, 08:15 · Crew A, Raju Yadav + 2

Vikram BhosaleArrive 09:00 Plot 27, Vidya Nagar, Indore 452001 Map Flat RCC roof. Water tank on the south-west corner, 1.8 m high. Customer knows you arrive at 09:00.
What to buildDrawing
Design
Rev B, option A, 12 modules
Size
5.4 kWp, 5 kW inverter
Structure
Elevated GI, 1.2 m at the low end
Shade
1 module in afternoon shade from the tank, as approved
Material loaded8 of 9
Steps and photos0 of 6 done
1
StructureDay 1 3 photos: base plates, frame level, low-end height Take photo0 of 3
2
ModulesDay 1 2 photos and scan 12 serials
3
DC wiringDay 1 2 photos: string connections, cable route
4
InverterDay 2 2 photos: mounted unit, serial label
5
EarthingDay 2 1 photo for each of 3 pits, lightning arrester
6
AC and ACDBDay 2 2 photos: ACDB, meter side. Power cut about 2 hours
Works without signal Photos stay on the phone and upload when it is back online. Pooja sees them on the project.
Day 1 done

Asks for any missing photo from steps 1 to 3 before closing the day.