Purchase orders
Fri 6 Nov 2026, 15:00
Receiving for KP-1042
All material inVikram Bhosale · PO-0318 and PO-0319 · received by Sameer Khan at the Kiranpath store
All material for KP-1042 is in: 9 of 9 lines
7 lines received on 3 GRNs, 2 held from store since Fri 30 Oct. The 70% payment of ₹2,11,680 is due on material delivery.
What Vikram seesRaise the 70% invoiceLines ready9 of 97 received, 2 from store
Received against POs₹2,06,528PO-0318 + PO-0319, incl. GST
Module serials12 of 12Scanned on GRN-0294
Open shortfalls0Earthing kit closed Thu 5 Nov
GRN-0291 for PO-0318Malwa Solar Traders · Wed 4 Nov, 16:30Closed by GRN-0292
| Item | Ordered | Received Wed 4 Nov | Received Thu 5 Nov | Status |
|---|---|---|---|---|
| Elevated GI structure kit | 1 set | 1 set | – | In full |
| DC cable 4 sq mm | 100 m | 100 m | – | In full |
| AC cable 6 sq mm | 30 m | 30 m | – | In full |
| ACDB + DCDB set | 1 | 1 | – | In full |
| Earthing pit kit (chemical) Shortfall of 1 recorded Wed 4 Nov, 16:30 | 3 | 2 | 1 GRN-0292, 11:00 | In full, Thu 5 Nov |
| Lightning arrester | 1 | 1 | – | In full |
GRN-0294 for PO-0319SponsoredVardhan PV, direct · Fri 6 Nov, 14:40Closed
| Item | Ordered | Received | Serials scanned | Damaged |
|---|---|---|---|---|
| 450 Wp DCR module | 12 | 12 | 12 of 12 | 0 |
Serials KPM450-2610-0048811 to KPM450-2610-0048822, checked against the handover list later
KPM450-2610-0048811KPM450-2610-0048812KPM450-2610-0048813KPM450-2610-0048814
KPM450-2610-0048815KPM450-2610-0048816KPM450-2610-0048817KPM450-2610-0048818
KPM450-2610-0048819KPM450-2610-0048820KPM450-2610-0048821KPM450-2610-0048822
From storeHeld for KP-1042 since Fri 30 Oct
| 5 kW on-grid string inverter | 1 | Serial recorded at installation |
| MC4 connector pair | 8 | 12 pairs stay free in store |
What happened
GRN-0294: 12 of 12 modules, serials scanned
Fri 6 Nov, 14:40 · Sameer
GRN-0292: third earthing kit in, shortfall closed
Thu 5 Nov, 11:00 · Sameer
GRN-0291: Malwa delivery, earthing 2 of 3
Wed 4 Nov, 16:30 · Sameer
PO-0318 and PO-0319 sent
Mon 2 Nov, 14:36 · after Nikhil approved at 14:35
Next for this project
Vardhan PV sees that PO-0319 was received in full. It does not see the other PO, the customer or the project price.