KP-1042 · Vikram Bhosale

Handover

5.4 kWp residential, on-grid · Vidya Nagar, Indore · Owner Pooja Sharma

WonEngineeringProcurementInstallationDISCOM and net meterHandover
Commissioned today at 15:30 by Raju Yadav DISCOM inspection passed Mon 16 Nov, net meter installed Wed 18 Nov. Expected generation 7,666 kWh a year, as approved in option A.
Serials, designed against installed13 of 13 match
ItemDesignReceivedInstalledSerialsResult
450 Wp DCR module1212
GRN-0294
12
Job card scan
KPM450-2610-0048811 to 004882212 of 12
5 kW on-grid string inverter11
From store
1
Job card scan
INV5K-26-77140Match

Serials scanned at receiving are compared with the ones Raju scanned on the roof. A module swapped on site would show here before the warranty papers go out.

As-builtSame as approved
As-built design
Rev B, option A, from Heaven Designs HD-20417
Changes on site
None recorded on the job card
System
12 modules, 5.4 kWp, 5 kW inverter, elevated GI structure 1.2 m at the low end
Approved by Vikram
Fri 30 Oct, 09:40
Commissioning evidence5 of 5 filed
Installation photos, 15From the job card, 6 steps, Tue 10 and Wed 11 NovFiled
Work completion reportSent to the DISCOM Thu 12 NovFiled
DISCOM inspectionPassed Mon 16 NovFiled
Net meter installedBy the DISCOM, Wed 18 NovFiled
Commissioning reportSynchronised with the grid, Thu 19 Nov 15:30Filed
PaymentsRecorded here, collected outside SurgePV
MilestoneShareAmountStatus
Advance20%₹60,480Received Wed 28 Oct
On material delivery70%₹2,11,680Received Sat 7 Nov
On commissioning10%₹30,240Invoiced today, due
Received so far₹2,72,160of ₹3,02,400 · ₹30,240 to come
Handover packSent

Sent to Vikram on WhatsApp at 15:58, with a link to his portal.

Commissioning report
Module and inverter warranties
DISCOM net-metering agreement
As-built drawing, rev B
User manual
See what Vikram sees
Still open after closing2

Subsidy is paid by the government to Vikram's bank, not to Kiranpath, and is never taken off his price.

What closing does

KP-1042 moves to Monitoring and leaves the execution board. The two open tasks keep their owners and stay on Pooja's list.

Activity

Handover pack sent on WhatsApp

Thu 19 Nov, 15:58 · Pooja

10% invoice sent, ₹30,240

Thu 19 Nov, 15:45 · Pooja

Commissioned and synchronised

Thu 19 Nov, 15:30 · Raju

Net meter installed by the DISCOM

Wed 18 Nov

DISCOM inspection passed

Mon 16 Nov · Raju