KP-1042 · Vikram Bhosale

Engineering

5.4 kWp residential, on-grid · Vidya Nagar, Indore · Owner Pooja Sharma

WonEngineeringProcurementInstallationDISCOM and net meterHandover
HD-20417 delivered at 18:10 as design revision B, 35 minutes before the due time of 18:45 Kavya Nair sent two options because the 1.8 m water tank shades the south-west corner in the afternoon. Neither goes to purchase until Vikram picks one.
Options against what was soldMarked cells differ from proposal v2
Sold, proposal v2Option A RecommendedOption B
Modules12 × 450 Wp DCR12 × 450 Wp DCR11 × 450 Wp DCR
System size5.4 kWp5.4 kWp4.95 kWp
Inverter5 kW string5 kW string5 kW string
StructureElevated GI, height to be fixedElevated GI, 1.2 m at the low endElevated GI, 1.2 m at the low end
ShadeNot assessed at sale1 module in partial afternoon shade from the tankNo shade
Generation a year7,830 kWh7,666 kWh
−164 kWh, −2.1%
7,178 kWh
−652 kWh, −8.3%
Price, GST included₹3,02,400₹3,02,400
Unchanged
₹2,77,200
−₹25,200, at ₹56,000 a kWp
Subsidy, separate₹78,000₹78,000₹78,000
Changes from what was sold–1 change
Generation only
4 changes
Modules, size, generation, price
Both options differ from what Vikram accepted, so he has to approve one before the buy list is made. Option B also changes his price. The subsidy stays ₹78,000 either way, because both systems are above 3 kW.
Option A layout12 modules
Roof plan: 2 rows of 6, tank shadow over 1 module after 15:00
Option B layout11 modules
Roof plan: 6 + 5, south-west slot left empty
Files in the packageRevision B · 7 of 7 delivered
FileCoversType
Roof layoutOptions A and BPDF
String planOptions A and BPDF
SLDOptions A and BPDF
Structural noteElevated GI, 1.2 m low end, clears most of the tank's winter afternoon shadowPDF
Shade reportTank 1.8 m, monthly loss per optionPDF
BOMOptions A and B; becomes the buy listCSV
DISCOM drawing setSanctioned load left blank: still unknownPDF
Request HD-20417Delivered

Placed, in design, 1 question answered, delivered.

Delivered
Thu 29 Oct, 18:10
Due
18:45, after a 45 min pause
Engineer
Kavya Nair
Revision
B, two options
Charge
₹3,481 on the October invoice
Kavya's note18:10
"I recommend option A. It keeps the size Vikram bought; one module loses some afternoon sun to the tank, about 2% a year. Option B drops that module and the shade, but makes about 490 kWh a year less than A."
What happens next
1
Send both options to Vikram's portal. He gets a WhatsApp message with the link.
2
He picks one. His choice is recorded with the time and the revision.
3
Aditya approves engineering, and the buy list is made from the chosen option.